Project Overview

Project Azure
Builder Iurada Property Group
Architect Interlandi Mantesso
Location Hampton, Victoria

THE PROJECT CHALLENGE / Develop a faster and easier to install system for the top level structure while still complying with the required building regulations.

THE CORTEK FRAMING STEEL SOLUTION /

> The lightweight alternative replaced substantial structural steel and was engineered to support the roof plan platform.>

> Fire rating allowances were accommodated within the Cortek framing design process, satisfying the FRL (fire resistant level) in accordance with AS 1530.

> Using the latest BIM modelling 3D technology, framing was detailed and fabricated to millimetre perfect accuracy.

> Cortek facilitated an on-site coordination meeting with the installer, site manager and project manager to ensure an efficient and streamlined install.

> The speed of erection was a key advantage of using steel, eliminating unnecessary fixings/brackets with no further straightening required once frames were installed.