Project Overview

Project Warrigal Road Day Care Centre
Builder Cardo Constructions
Architect T3 Architecture
Location Ashburton, Vic

THE PROJECT CHALLENGE /

Develop an alternative framing system to reduce structural steel and save time on install.

THE CORTEK FRAMING STEEL SOLUTION /

The light gauge steel framing system was fully engineered to achieve the required design and structural properties, removing unnecessary and costly structural steel.

Frames were fabricated using 3D CAD integrated machinery for straight, true and accurate results, resulting in faster erection.

As a result of the efficiencies in the install process, the project was completed approximately 2 months ahead of expected deadlines.

In the words of the builder:

Blue is the future.