THE PROJECT CHALLENGE /

A pre-fabricated system was required to support a 7.5kPa snow load without jeopardising the ceiling height, achieve the required BAL rating and enable quick erection on site due to limited construction time frames.

THE CORTEK FRAMING STEEL SOLUTION /

Top level walls and trusses were detailed, engineered and fabricated in-house to withstand heavy snow. Frames were delivered in time before the winter season set in.

The light gauge steel framing solution replaced a portal framed system with infilled metal framing, satisfying the fire engineering requirements.

The frames were extremely accurate to the shop drawings and as the frames were pre-fabricated, the erection process was reduced by at least half the time compared to a stick build approach – saving approximately 4-6 weeks.

Steel framing does not bow or twist which meant that the services and finishing trades were able to rough in without any framing straightening required.