THE PROJECT /
Stage 2 of Melbourne Park’s redevelopment included the construction of a new Admin and Media Building, serving as the headquarters for Tennis Australia and Melbourne and Olympic Park’s Trust.
The project posed a significant challenge with a unique eyebrow cantilevered truss facade requiring a lightweight yet structurally sound solution.
THE CORTEK STEEL FRAMING SOLUTION /
Cortek provided a pre-fabricated lightweight steel framing system that replaced the proposed structural steel, meeting all cantilever and engineering requirements.
Frames were fully designed, engineered, and shop detailed to support direct-fix cladding and were craned into place using custom brackets. With no need for top hats or infill purlins, the system allowed for faster, more efficient installation.
Modules were manufactured to site specifications and delivered pre-clad to align with the project schedule.