When it comes to construction, time is money—and one of the biggest advantages of using pre-fabricated (prefab) building methods over traditional stick build is the reduction in installation time. But just how much time are we really talking about?

 

A Rule of Thumb: 33% Time Saving

When choosing between traditional construction methods and modern alternatives, pre-fabricated light gauge steel frames are becoming the go-to for builders aiming to save time without compromising structural integrity.  On average, projects that utilise steel prefab frames see a time saving of about 33% compared to traditional stick building. That means if the stick-built method would take 30 days, switching to pre-fabricated frames can cut that down to around 20 days—saving roughly 80 hours per labourer on a standard 8-hour workday schedule.

This efficiency comes from factory-controlled fabrication, value managed frame designs, reduced material and minimised on-site assembly. Components arrive ready to install, removing the variability and delays often experienced with timber framing on-site.

 

Real-World Proof: Marian College Learning Hub

Take the Marian College project in Sunshine West as a prime example. The team initially allocated a full week for the internal wall frame installation using standard assumptions—but by using pre-fabricated light gauge steel frames from Cortek, the structure was fully installed in just 2 days. That’s a 71% time saving, a reduction from 40 hours to only 16. The precision fit of the prefab components meant faster erection times, fewer errors, and no waiting on-site for timber cutting.

 

Lionheart Reserve – Tennis Pavilion: Another Win for Prefab Steel

Similarly, the Lionheart Reserve project in Taylors Lake had originally been scheduled for 3 days of install, yet was completed in 2 days using a prefab external wall framing system. That’s a 33% saving, reducing the install time from 24 to 16 hours. The pre-engineered steel walls arrived from Cortek ready to erect, allowing the crew to work faster and more efficiently than they could with traditional on site timber.

 

Taking Inspiration From Around the World

Located in Teton County, Wyoming, the resort town of Jackson is home to Sagebrush, a 90-unit residential building. The framing for the four-story structure was supplied by Douglass Colony, which utilised FRAMECAD’s advanced manufacturing technology to reduce the framing schedule by up to 75%.

All light gauge steel panels and trusses were prefabricated off-site and delivered directly to the construction site, significantly streamlining the build process. As a result, the project was completed on time—in just four months.

For more details, read the full story here.

 

The Bottom Line – Why It Matters

Switching to pre-fabricated light gauge steel framing doesn’t just save time—it transforms the entire building process. Whether you’re aiming to reduce costs, speed up delivery, or improve site efficiency, the time saved translates directly into higher productivity and greater project profitability.

From a conservative 30% time reduction to real-world examples showing 70%+ savings, the numbers speak for themselves. As more builders adopt prefab steel solutions, the question is less “why” and more “when.”

This kind of time savings has a domino effect across the entire construction timeline. Projects can be handed over to clients faster, crews can move on to the next job sooner, and companies can save on costs related to labour, equipment rentals and site logistics. In a competitive industry, being faster without compromising quality is a game-changer.

 

Ready to Save Time on Your Next Project?

If you’re interested in learning how pre-fabricated light gauge steel frames can speed up your next build, get in touch with our team today. We’ll walk you through the process, provide expert insights, and help you find the best solution to suit your project timeline and budget.

Contact our team on 1300 782 950 or send your plans for customised proposal.

 

Image of Sagebrush – Courtesy of FRAMECAD